Miraein Logis Bucheon Complex Logistics Center
- Term
- 2021.04. ~ 2024.05.
- Client
- Miraein Logis Bucheon PFV
- Location
- Bucheon-si, Gyeonggi-do
- Type
- Industrial Logistics Center
- Total Floor Area
- B2F~12F Total floor area 81,663㎡

Value Engineering (VE) Proposals: 35 Cases
Through the tracking management of Value Engineering (VE) Proposal, the project technician checks whether it is reflected throughout the construction duration, and the VE leader in the headquarters leads the tracking and aggregation and checks whether the VE Proposal is well planned or not. For the Bucheon Complex Distribution Center project, 31 out of 35 Value Engineering (VE) Proposal ideas were adopted, resulting in a reduction in the total construction cost of KRW 7.8 billion.

DX (Digital Transformation) Realization utilizing Smart Construction Collaboration TOOL
Bucheon Complex Distribution Center project introduced a system to support the digital transformation of construction management. Digitalization of documents related to inspection, quality, and materials reduces work stages and management time by 50%, leading to increased efficient work performance.